Configure the Default Due Date for RFIs
Configure the Default Due Date for RFIs
Perform the following steps to configure the default due date for RFIs.
You must be a Project Administrator to configure the default due date.
To configure the default due date for RFIs
Select Administration > Module Configuration from the right navigation panel of the RFIs module.
Select the desired number of days from the Default Due Date for RFIs dropdown. Select whether you want the default due date calculated based on business days or calendar days.
Set the same options as needed for the Default Due Date for Secondary Reviewers to Return RFIs.
The project default is 7 days. The secondary reviewer due date is set to 4 days by default.
Scroll to the bottom of the RFI Configuration section and select Save Settings to save your changes.